Avalon Repaving 2025
Avalon will be repaving our surface roads as well as parking lots in various stages from July 20th – August 5th 2025.
Repaving schedule below:
- July 20th at 9pm – July 22nd at 6am: 1st Street and Eastside of 6000 Parking Lot
- July 21st at 9pm – July 23rd at 6am: East side of Arhaus Lot and North Deck North Surface Lot
- July 22nd at 9pm – July 24th at 6am: Westside of Arhaus lot and Westside of 6000 lot
- July 23rd at 9pm – July 25th at 6am: South lot of Whole Foods and South lot of Container Store
- July 24th at 9pm – July 26th at 6am: Strip by Container Store and Southside of 7000 Surface Lot
- July 26th at 9pm – July 28th at 6am: Parkdale Lane and PNC Bank
- July 27th at 9pm – July 29th at 6am: Northside Container Store Northside 7000 Surface Lot
- July 28th at 9pm – July 30th at 6am: 3rd Street Entrance and Northside of Whole Foods Surface lot
- July 29th at 9pm – July 31st at 6am: Phase 1 Blvd
- July 30th at 9pm – Aug 1st at 6am: Phase 2 Blvd and Southside of 1st Street
- Aug 3rd at 9pm – Aug 5th at 6am: 2nd Street and South Parking Deck Surface Lot
- Aug 4th at 9pm – Aug 6th at 6am: 3rd Street Entrance and Northside of Whole Foods Surface lot
- Aug 5th at 9pm – Aug 7th at 6am: 1st Street Central and Avalon Way
Please email management@expeirenceavalon.com with questions or concerns.